Survey Information

WHAT

YOU SHOULD KNOW

ABOUT HAVING

YOUR LAND SURVEYED

Click Here for more Information

 

 

 

 

 

Civil Engineering > Sanitary Sewer Projects

Hill Street Lift Station -- Sapulpa, OK
Turley 16" Force Main -- Tulsa, OK
Unsewered Area 36th St. N. & Harvard --Tulsa, OK
Westside Outfall -- Skiatook, OK
Dewar Lagoon Improvements -- Dewar, OK
Tenkiller State Park Sewer Improvements -- Vian, OK
EOSC Sewer System Evaluation Survey -- Wilburton, OK
Claremore I/I Monitoring Study -- Claremore, OK
Joe Creek Relief Sewer Phase I & II -- Tulsa, OK
Sanitary Sewer and Lagoon Rehabilitation -- Fairland, OK
Wastewater Treatment & Collection System -- Sand Springs, OK


Civil Engineering > Sanitary Sewer Projects
Hill Street Lift Station -- Sapulpa, OK

A 628 gpm sewage lift station and 1,480 feet of 8" force main were designed for the City of Sapulpa to serve a new residential subdivision and surrounding areas.

The design included a determination of the lift station site and force main route. Design considerations for the lift station included sizing the pumps and motors, sizing the wet well, storage calculations, buoyancy check, and capacity of downstream gravity sewers and lift station.

The project is to be constructed in two phases. The project components were sized for alternate use wherever practical.

Special consideration was given to keeping the existing lift station in service during construction. Also, the existing wet well was retained for emergency holding capacity.
Project List

Civil Engineering > Sanitary Sewer Projects
Turley 16" Force Main -- Tulsa, OK

The purpose of this project was to design a replacement for a 6,000 foot, forty-year old, 16" sewage force main in north Tulsa. A major project constraint was to keep the existing force main in service until the switch to the new force main could be made. The lift station could only be taken out of service for a short time during low flow.

The firm designed the pipeline to accommodate two alternative pipe materials - ductile iron and high density polyethylene (HDPE). The line was routed to minimize the need for new easements. We prepared an easement for the area through property owned by Tulsa County.
Route survey was performed by in-house survey crews.

Other services included preparing an engineering cost estimate and writing a special specification section for HDPE pipe. There were two creek crossings on the project.
We attended the bid opening, tabulated bids, and made recommendation of award. When the project was completed, we prepared record drawings.
Project List

Civil Engineering > Sanitary Sewer Projects
Unsewered Area 36th St. N. & Harvard -- Tulsa, OK

The firm was hired to design sanitary sewer service to an unsewered area bounded by 36th Street North and Highway 11 and Highway 75 and North Harvard.

The firm provided a property search to establish all property owners and existing rights-of-way and easements. A preliminary route location was made to demonstrate that all property owners that had petitioned the City for sewer service could be sewered. We prepared exhibits and attended a public meeting to discuss the project with the residents. The locations of the sewer lines was revised according to information received from the public.

Construction plans and specifications were then developed and the project was bid. The profiles were developed using information from in-house survey crews. We provided easement descriptions and plats as required for the new sewer lines. General services during construction were provided including bidding assistance, submittal review, pay request review, and periodic inspections.
Project List

Civil Engineering > Sanitary Sewer Projects
Westside Outfall -- Skiatook, OK

The firm completed an engineering study and design of an outfall sewer to serve the west side of Skiatook. The outfall opened up a large area for development and allowed Skiatook to eliminate an existing lift station.

During the study phase, future sewage flows were projected and a final route was selected. Easement requirements were identified.

Construction plans and specifications were produced during the design phase. We also prepared all easement plats and descriptions. Sewer sizes and slopes were designed to meet the ultimate flow requirement. The final project included about 13,000 linear feet of 18" pipe, almost 1,500 linear feet of 15" pipe, three road crossings, and forty manholes.
Bidding and Construction Phase services included bidding assistance, bid tabulation, preconstruction conference, submittal review, periodic inspection, pay request review, final inspection and as-built drawings.
Project List

Civil Engineering > Sanitary Sewer Projects
Dewar Lagoon Improvements -- Dewar, OK

The firm designed improvements to the Dewar four cell lagoon system, which included the following:

18" sanitary outfall
New flow splitter box
Demolition of existing by-pass drains
Fencing
Rehabilitation of a discharge flow structure with weir
Reshaping of lagoon slopes and dikes
Placing gravel on top of dikes
Sludge removal with land application of sludge

The project was bid in two packages. One contract was for the rehabilitation work and the other was for the sludge removal and land application.

General services during construction included bidding assistance, Prework Conference, submittal review, pay estimate review, periodic and final inspection and as-built drawings.
Project List

Civil Engineering > Sanitary Sewer Projects
Tenkiller State Park Sewer Improvements -- Vian, OK

An engineering study was conducted for the Tenkiller State Park sewage system. Items investigated included existing pump stations, force mains, gravity lines, and total retention lagoons. Specific problems included old pumps, wet wells below the lake flood pool elevation, lagoons which overflow and leak, inflow sources, inadequate area for lagoons and plumbing fixtures that do not conserve water.

Eight new pump stations were designed. One of the pump stations was specifically designed to be water resistant during high water periods. New lagoons with about 9 acres of surface area were designed to replace the existing lagoons, which had less than three surface acres.
A sludge management plan for beneficial reuse of the sludge by land application was prepared. The plan was for disposal of the sludge in the existing lagoon cells.

The size of the new cells was minimized by designing supplemental land application by spray irrigation.

A Stormwater Pollution Prevention Plan was written including an erosion control plan.

All field surveys were done with in-house crews using total station and GPS equipment.
Project List

Civil Engineering > Sanitary Sewer Projects
EOSC Sewer System Evaluation Survey -- Wilburton, OK

The firm acted as the College's consultant in response to a notice of violation from the Department of Environmental Quality (DEQ). A study was conducted to investigate existing problems concerning the sanitary sewer collection system comprised of 30 manholes and 8,020 linear feet of 8" line, most of which was constructed when the College was originally built.

Inspection and testing in Phase I of the evaluation included physical inspection of all manholes, smoke testing of the entire system and electronic flow measurement of a critical manhole over a period of two months which included dry and wet periods. A detailed infiltration/inflow analysis was performed on the entire collection system to develop hydrographics and evaluate the extent of infiltration/inflow on the system.

The existing lagoon was analyzed and alternatives were investigated to determine the optimum manner in which to increase the lagoon's treatment capacity and to bring the lagoon into compliance with DEQ regulations.

Other services included making recommendations on tying the College sewer system to the Wilburton Municipal Sewer System. A detailed report was submitted to EOSC.

Phase II of the sewer system study included cleaning and television internal inspection of 5,200 linear feet of 6" and 8" line. The firm coordinated the work and incorporated the results of the inspection into a final report which included specific rehabilitation recommendations as a basis for construction plans.

The final phase of the project included the preparation of plans and specifications for the recommended rehabilitation of the existing sewer system, including slip-lining, manhole rehabilitation, replacement lines and point repairs. Services during bidding and construction were provided.
Project List

Civil Engineering > Sanitary Sewer Projects
Claremore I/I Monitoring Study -- Claremore, OK

Sanitary sewage flow was monitored at fourteen locations in Claremore for a period of 90 days. Badger flow meters were used along with four electronic rain gages which were recorded by four of the flow monitors.

The City was divided into thirteen subbasins for the study. Flow hydrographs were developed for wet and dry conditions for each of the subbasins. This information was used to develop unit hydrographs for use in a computer model of the sewage collection system.

All pipes 10" and larger were input to a computer model which was used to predict potential overflow locations. All manholes were numbered for use in the model and for future identification.

Based on the information gathered, peak flows were predicted for rainfall events. The subbasins were ranked in terms of infiltration and inflow per inch diameter mile of pipe.

As a part of the study, four lift stations were evaluated. The pumping rates were calculated by drawdown tests. Recommendations were made concerning adequacy and potential problems.

As a result of the study, the City was prepared to proceed to a physical investigation and television inspection phase.
Project List

Civil Engineering > Sanitary Sewer Projects
Joe Creek Relief Sewer Phase I & II -- Tulsa, OK

The firm was retained to provide a route location study for 20,000 linear feet of sanitary sewer relief main from 55th and Delaware to 29th and Yale in the City of Tulsa. The contract included final design of the portion from 55th and Delaware to 38th and Sandusky. The original sanitary sewer line had chronic overflow problems at numerous manholes locations during times of heavy rainfall due to storm water infiltration. The original sanitary sewer line went through a highly urbanized part of the City, containing both commercial and residential development, and included the crossing of Joe Creek concrete lined channel, primary arterial streets, and a section of interstate highway.

The diameter sizes of the sewer relief main were designed to be 15, 18, 21, 24 and 30 inches, depending on the anticipated storm water infiltration of the original sewer. Cross-connections were determined at key locations, allowing the maximum amount of storm water to be discharged into the new relief sewer main.

Several route locations were analyzed to determine the least cost and the best maintenance accessible. Because part of the construction was to take place in an older established residential area, special consideration was given to the property owners' concerns, such as the prevention of damage to trees, driveways, and streets. Borings were specified whenever the relief line passed beneath the drip line of a large tree, special structure or obstacle that was of concern to the property owner or the City of Tulsa.

In-house survey crews were used for the design survey. Detailed location surveys and profiles were done. Also, property surveys were needed to locate property corners. Easement descriptions were prepared for portions of the line placed outside existing right-of-way or easements.

All types of manholes, i.e., standard, drop, special design and manhole connections, were used in this project. Special designs for oversize manholes were used when both the existing line and relief line were to be in the same structure.

Construction services provided by the firm include bidding assistance, bid tabulation, preconstruction conference, shop drawing review, periodic inspection, resident inspection, construction staking, contractor's pay request review, final inspection and as-built drawings.
Project List

Civil Engineering > Sanitary Sewer Projects
Sanitary Sewer and Lagoon Rehabilitation -- Fairland, OK

The firm was retained to design sanitary sewer rehabilitation and lagoon rehabilitation for the town of Fairland, Oklahoma, in response to a Consent Order from the Oklahoma State Department of Health. The NPDES permit limitations were being exceeded at the Town's flow-through lagoons and one of the potable water wells was testing above limits for radium.

Design was based on several studies done by the firm. The first study included flow monitoring, smoke testing and physical inspection of the system to determine infiltration and inflow effects. Recommendations were made concerning which lines and manholes should be rehabilitated or removed, etc.

The second study addressed the beneficial reuse of sludge by land application. The two older lagoon cells were to be cleaned by removing the sludge. The beneficial reuse study investigated the feasibility of land application. Application rates were determined, and suitable farm land was located. Removal methodology was developed and described in the study.

Plans and specifications were developed which reflected the recommendations of the reports. Approximately one mile of 8" and 10" gravity sewer was replaced and 2,000 feet of 6" force main was installed. The contract also called for 11,000 feet of cleaning and TV inspection.

Other services included bidding assistance, bid tabulation, prework conference, submittal review, pay estimate review, periodic and final inspection and as-built plans.

All work was done in strict compliance with requirements and time schedules set forth in the Consent Order.
Project List

Civil Engineering > Sanitary Sewer Projects
Wastewater Treatment & Collection System -- Sand Springs, OK

The firm was responsible for the planning and design of a sewage collection and treatment system to serve a previously unsewered area. Facilities included 8", 10" and 21" gravity sewer pipe, 10" pressure pipe and a sewage lift station. The system was designed to serve an ultimate area of about 750 acres. A preliminary study was done to allow accurate sizing of facilities based on developable land and actual topographic characteristics. All field surveying was done in-house using Zeiss self-leveling level and optical electric distance measuring device mounted on a Wild T2A 5-second theodolite.

The sewage treatment facility consisted of a four-cell lagoon system. Due to the initial low flows anticipated, the system acted as a total retention lagoon in the early stages of development. It was designed to be converted to a flow-through system when flows increased. At maximum design flows, aerators can be added and the depth increased with weir to allow the system to function as an aerated flow-through system.

Complete construction plans were prepared with specifications and cost estimates. Services during construction included construction staking, periodic inspection, pay estimate review, final inspection and as-built drawings.
Project List

 
Copyright © 2008.Breisch & Associates, Inc..All Rights Reserved.