Survey Information

WHAT

YOU SHOULD KNOW

ABOUT HAVING

YOUR LAND SURVEYED

Click Here for more Information

 

 

 

 

 

Civil Engineering > Water Line Projects

24" Northside Transmission Water Line -- Sapulpa, OK
20" Water Line Extension -- Sapulpa, OK
24" Water Main -- Tulsa, OK
Pump Station Modification -- Dewar, OK
60" Water Supply Line -- Tulsa, OK
48" Water Supply Line -- Tulsa, OK
209th Street Booster Pump Station -- Sand Springs, OK
McKinley Water Line -- Sand Springs, OK
41st Street 16" Water Line Relocation -- Tulsa County, OK

Civil Engineering > Water Line Projects
24" Northside Transmission Water Line -- Sapulpa,

Engineering services were provided for all phases of the project, including construction administration and resident inspection for three miles of 24" water transmission line, from the Sapulpa Water Treatment Plant to the water tower on Highway 97. The project involved route selection and easement negotiations.

Detailed design surveys were performed to establish vertical and horizontal control and to obtain topographic features. Field notes were directly converted to drawings using Computer Aided Drafting and Design (CADD) equipment and "AutoCAD" software.

Ductile iron, PVC and Polyethylene pipe materials were permitted. The bid included an alternate for 24" pipe. Thrust was controlled by the use of concrete blocking and restrained joints.

Easement descriptions and plats were prepared for a dozen property owners.
Project List

Civil Engineering > Water Line Projects
20" Water Line Extension -- Sapulpa, OK

Engineering services were provided for all phases of the project, including construction administration and resident inspection for 3,000 feet of 20" water transmission line, from the 5th Street Reservoir to Division Street. The project included route selection.

Detailed design surveys were performed to establish vertical and horizontal control and to obtain topographic features. Field notes were directly converted to drawings using Computer Aided Drafting and Design (CADD) equipment and "AutoCAD" software.

Ductile iron, PVC and Polyethylene pipe materials were permitted. Thrust was controlled by the use of restrained joints.

Easement descriptions and plats were prepared for three property owners.

The design included installation of an 8" pressure reducing valve in an existing vault. A 12" altitude valve was also installed in an existing vault that was modified. Modification of the vault included strengthening the sides and adding a fiberglass shelter.
Project List

Civil Engineering > Water Line Projects
24" Water Main -- Tulsa, OK

Engineering services were provided for all phases of the project, including construction administration, resident inspection and construction staking for a two and one-half (2.5) mile long 24" water main from 56th Street North and Hartford to 66th Street North and Lewis Avenue. The project involved route selection taking into consideration existing utilities, construction obstructions and construction costs.

Detailed design surveys were performed to establish vertical and horizontal control and to obtain topographic features. Field notes were directly converted to drawings using Computer Aided Drafting and Design (CADD) equipment and "AutoCAD" software.

Alternative types of pipe: Ductile iron, steel and reinforced concrete. Thrust pressures were controlled by the use of concrete blocking and restrained joints.

Right-of-way descriptions and plats were prepared for the areas where inadequate right-of-way existed.
Project List

Civil Engineering > Water Line Projects
Pump Station Modification -- Dewar, OK

A water booster pump station was rehabilitated by replacing two pumps and motors. Motors were sized at 15 horsepower. All valving was also changed out. Other work included resetting the electronic controls for remote operation.

A telemetry cable was designed and routed. Part of the cable was placed overhead and a portion was buried.

We assisted with bidding and contract award. Services during construction included shop drawing review, preconstruction conference, pay request review, periodic and final inspection, change orders and as-built drawings.
Project List

Civil Engineering > Water Line Projects
60" Water Supply Line -- Tulsa, OK

The firm was retained by the City of Tulsa to design and inspect three and one-half (3.5) miles of 60" water main. Detailed field surveys were made to establish vertical and horizontal control and to locate all obstructions. The firm was responsible for recommending the most feasible route and alignment considering the location of existing utilities and other obstacles. Right-of-way requirements were determined and legal descriptions and plats prepared.

Plan and profile drawings were plotted directly from field notes using an IBM computer with AutoCAD software. Design calculations were run for steel, ductile iron and steel cylinder concrete pressure pipe. When required, thrust was controlled by designing thrust blocking and restrained joints. Effects of surge were analyzed to determine the need for additional surge protection in the system.

The project included large fittings and 48" valves. The spacing of the valves and outlets was studied. Corrosion control was designed for the ductile iron and steel pipe alternatives.
At one end, the line was connected to an existing 60" line. At the other end, coordination was made with another A/E who was designing an adjacent project.

The firm provided a resident project representative. Other services included cost estimates, bidding assistance, shop drawing review, pay estimate review, periodic inspection, final inspection and as-built drawings.
Project List

Civil Engineering > Water Line Projects
48" Water Supply Line -- Tulsa, OK

As part of a major water expansion project, the firm was retained by the City of Tulsa to design and inspect two miles of 48" water main. Detailed field surveys were made to establish vertical and horizontal control. All obstructions were located. The firm was responsible for recommending the most feasible route and alignment considering the location of existing utilities and other obstacles. Right-of-way requirements were determined and legal descriptions and plats prepared.

Photogrammetry was used for the plan view and to determine the centerline profile of the ground at the pipe location. Design calculations were run for steel, ductile iron and steel cylinder concrete pressure pipe. Where required, thrust was controlled by designing thrust blocking and restrained joints.

The project included large fittings, 24" butterfly valves and 30" ball valves in structural concrete vaults. Corrosion control was designed for the ductile iron and steel pipe alternatives. A design for the connection to existing facilities was done for one end of the project. The other end was designed to allow future connections without interruption of water service.

The firm was responsible for resident inspection. Other services included detailed cost estimate, assistance during bidding, shop drawing review, contractor's pay estimate review and as-built drawings.
Project List

Civil Engineering > Water Line Projects
209th Street Booster Pump Station -- Sand Springs, OK

The firm was retained to provide plans and specifications for a 300 G.P.M. water booster pump station and 50,000 gallon above ground water storage tank. The pumps were to provide needed pressure to the water distribution system northwest of the City.

Site survey was done by in-house field crew using electronic "Total Station" equipment. Data was transferred directly to the firm's CADD system, AutoCAD, for preparation of the topography plan.

The design called for an above ground duplex pump station, skid mounted, inside a concrete masonry unit structure. The structure was detailed by the firm's in-house architectural staff.
Site design included yard piping, entrance drive and culvert, grading, gravel parking area, valve vault and locations.

A telemetry system was specified which was compatible with the City's existing telemetry systems. The telemetry allowed control and observation from the central unit at the water treatment plant.

Specifications were prepared to cover all items of work, and a cost estimate was prepared.
The firm assisted with advertising and bidding, tabulated bids and made recommendation of award. Construction services included submittal review, pay estimate review, periodic and final inspection, and as-built drawings.
Project List

Civil Engineering > Water Line Projects
McKinley Water Line -- Sand Springs, OK

The firm was retained to design 4,000 feet of 12" water line to replace an existing 6" water line. The work involved hydraulic analysis to determine whether modifications were needed for an existing booster pump station located at the downstream end of the water line project.

KYPipe software was used for the hydraulic study. The model included three booster pump stations and a water storage tank. Runs were made considering the 12" pipe alone and in parallel with the existing 6" pipe. A fully documented report was prepared for the client.

Extensive field surveying was done with in-house survey field crews. Right-of-way was established and easement descriptions were prepared.

Plan and profile sheets were produced along with sufficient details for connections, etc. Also contract documents, technical specifications and cost estimates were produced.

Bidding and construction services included advertising, tabulation of bids, recommendation of award, preconstruction conference, shop drawing review, pay request approval, periodic inspection, final inspection and as-built drawings.
Project List

Civil Engineering > Water Line Projects
41st Street 16" Water Line Relocation -- Tulsa County, OK

The firm was retained to prepare construction plans and documents for the relocation of one mile of 16” ductile iron water line, which was necessary due to improvements on West 41st Street. The line was relocated in about eight separate locations to avoid interference with the road construction.

Plan and profile sheets from the 41st Street improvements, which the company had also designed, were used as base sheets for the construction drawings. In-house survey crews went to the field to sound the existing line and verify its location. The drawings were produced with AutoCAD.

Included in the project were several road crossing relocations involving 6” and 8” water lines as well as about 200 feet of 15” and 300 feet of 8” sanitary sewer with manholes.

Road boring was done for 30”, 24” and 18” steel conduits for the water and sewer lines as well as some 4” PVC conduit for service line crossings. About four water meters were relocated as part of the project.

The design was coordinated with the Oklahoma Department of Transportation and Tulsa County.

Engineering services during construction included prework conference, submittal review, pay request review, periodic and final inspection and as-built drawings. The firm also provided resident inspection for this project.
Project List

 
Copyright © 2008.Breisch & Associates, Inc..All Rights Reserved.