| |
|
Engineering services were provided for all phases of the project, including
construction administration and resident inspection for three miles of
24" water transmission line, from the Sapulpa Water Treatment Plant
to the water tower on Highway 97. The project involved route selection
and easement negotiations.
Detailed design surveys were performed to establish vertical and horizontal
control and to obtain topographic features. Field notes were directly
converted to drawings using Computer Aided Drafting and Design (CADD)
equipment and "AutoCAD" software.
Ductile iron, PVC and Polyethylene pipe materials were permitted. The
bid included an alternate for 24" pipe. Thrust was controlled by
the use of concrete blocking and restrained joints.
Easement descriptions and plats were prepared for a dozen property owners.
Project List
Engineering services were provided for all phases of the project, including
construction administration and resident inspection for 3,000 feet of
20" water transmission line, from the 5th Street Reservoir to Division
Street. The project included route selection.
Detailed design surveys were performed to establish vertical and horizontal
control and to obtain topographic features. Field notes were directly
converted to drawings using Computer Aided Drafting and Design (CADD)
equipment and "AutoCAD" software.
Ductile iron, PVC and Polyethylene pipe materials were permitted. Thrust
was controlled by the use of restrained joints.
Easement descriptions and plats were prepared for three property owners.
The design included installation of an 8" pressure reducing valve
in an existing vault. A 12" altitude valve was also installed in
an existing vault that was modified. Modification of the vault included
strengthening the sides and adding a fiberglass shelter.
Project List
Engineering services were provided for all phases of the project, including
construction administration, resident inspection and construction staking
for a two and one-half (2.5) mile long 24" water main from 56th Street
North and Hartford to 66th Street North and Lewis Avenue. The project
involved route selection taking into consideration existing utilities,
construction obstructions and construction costs.
Detailed design surveys were performed to establish vertical and horizontal
control and to obtain topographic features. Field notes were directly
converted to drawings using Computer Aided Drafting and Design (CADD)
equipment and "AutoCAD" software.
Alternative types of pipe: Ductile iron, steel and reinforced concrete.
Thrust pressures were controlled by the use of concrete blocking and restrained
joints.
Right-of-way descriptions and plats were prepared for the areas where
inadequate right-of-way existed.
Project List
A water booster pump station was rehabilitated by replacing two pumps
and motors. Motors were sized at 15 horsepower. All valving was also changed
out. Other work included resetting the electronic controls for remote
operation.
A telemetry cable was designed and routed. Part of the cable was placed
overhead and a portion was buried.
We assisted with bidding and contract award. Services during construction
included shop drawing review, preconstruction conference, pay request
review, periodic and final inspection, change orders and as-built drawings.
Project List
The firm was retained by the City of Tulsa to design and inspect three
and one-half (3.5) miles of 60" water main. Detailed field surveys
were made to establish vertical and horizontal control and to locate all
obstructions. The firm was responsible for recommending the most feasible
route and alignment considering the location of existing utilities and
other obstacles. Right-of-way requirements were determined and legal descriptions
and plats prepared.
Plan and profile drawings were plotted directly from field notes using
an IBM computer with AutoCAD software. Design calculations were run for
steel, ductile iron and steel cylinder concrete pressure pipe. When required,
thrust was controlled by designing thrust blocking and restrained joints.
Effects of surge were analyzed to determine the need for additional surge
protection in the system.
The project included large fittings and 48" valves. The spacing of
the valves and outlets was studied. Corrosion control was designed for
the ductile iron and steel pipe alternatives.
At one end, the line was connected to an existing 60" line. At the
other end, coordination was made with another A/E who was designing an
adjacent project.
The firm provided a resident project representative. Other services included
cost estimates, bidding assistance, shop drawing review, pay estimate
review, periodic inspection, final inspection and as-built drawings.
Project List
As part of a major water expansion project, the firm was retained by
the City of Tulsa to design and inspect two miles of 48" water main.
Detailed field surveys were made to establish vertical and horizontal
control. All obstructions were located. The firm was responsible for recommending
the most feasible route and alignment considering the location of existing
utilities and other obstacles. Right-of-way requirements were determined
and legal descriptions and plats prepared.
Photogrammetry was used for the plan view and to determine the centerline
profile of the ground at the pipe location. Design calculations were run
for steel, ductile iron and steel cylinder concrete pressure pipe. Where
required, thrust was controlled by designing thrust blocking and restrained
joints.
The project included large fittings, 24" butterfly valves and 30"
ball valves in structural concrete vaults. Corrosion control was designed
for the ductile iron and steel pipe alternatives. A design for the connection
to existing facilities was done for one end of the project. The other
end was designed to allow future connections without interruption of water
service.
The firm was responsible for resident inspection. Other services included
detailed cost estimate, assistance during bidding, shop drawing review,
contractor's pay estimate review and as-built drawings.
Project List
The firm was retained to provide plans and specifications for a 300 G.P.M.
water booster pump station and 50,000 gallon above ground water storage
tank. The pumps were to provide needed pressure to the water distribution
system northwest of the City.
Site survey was done by in-house field crew using electronic "Total
Station" equipment. Data was transferred directly to the firm's CADD
system, AutoCAD, for preparation of the topography plan.
The design called for an above ground duplex pump station, skid mounted,
inside a concrete masonry unit structure. The structure was detailed by
the firm's in-house architectural staff.
Site design included yard piping, entrance drive and culvert, grading,
gravel parking area, valve vault and locations.
A telemetry system was specified which was compatible with the City's
existing telemetry systems. The telemetry allowed control and observation
from the central unit at the water treatment plant.
Specifications were prepared to cover all items of work, and a cost estimate
was prepared.
The firm assisted with advertising and bidding, tabulated bids and made
recommendation of award. Construction services included submittal review,
pay estimate review, periodic and final inspection, and as-built drawings.
Project List
The firm was retained to design 4,000 feet of 12" water line to
replace an existing 6" water line. The work involved hydraulic analysis
to determine whether modifications were needed for an existing booster
pump station located at the downstream end of the water line project.
KYPipe software was used for the hydraulic study. The model included three
booster pump stations and a water storage tank. Runs were made considering
the 12" pipe alone and in parallel with the existing 6" pipe.
A fully documented report was prepared for the client.
Extensive field surveying was done with in-house survey field crews. Right-of-way
was established and easement descriptions were prepared.
Plan and profile sheets were produced along with sufficient details for
connections, etc. Also contract documents, technical specifications and
cost estimates were produced.
Bidding and construction services included advertising, tabulation of
bids, recommendation of award, preconstruction conference, shop drawing
review, pay request approval, periodic inspection, final inspection and
as-built drawings.
Project List
The firm was retained to prepare construction plans and documents for
the relocation of one mile of 16” ductile iron water line, which
was necessary due to improvements on West 41st Street. The line was relocated
in about eight separate locations to avoid interference with the road
construction.
Plan and profile sheets from the 41st Street improvements, which the company
had also designed, were used as base sheets for the construction drawings.
In-house survey crews went to the field to sound the existing line and
verify its location. The drawings were produced with AutoCAD.
Included in the project were several road crossing relocations involving
6” and 8” water lines as well as about 200 feet of 15”
and 300 feet of 8” sanitary sewer with manholes.
Road boring was done for 30”, 24” and 18” steel conduits
for the water and sewer lines as well as some 4” PVC conduit for
service line crossings. About four water meters were relocated as part
of the project.
The design was coordinated with the Oklahoma Department of Transportation
and Tulsa County.
Engineering services during construction included prework conference,
submittal review, pay request review, periodic and final inspection and
as-built drawings. The firm also provided resident inspection for this
project.
Project List
| |